Telic Engineering / Field notes

Field notes. From the job.

Short practical notes from gas turbine controls, instrumentation and commissioning work. The same notes Remco posts on LinkedIn, kept in one place.

· Week 49 · Latest

Overspeed protection checks

Overspeed protection is the one turbine function that has to work the first time it is needed.
Proving the overspeed trip. Overspeed protection: speed wheel with three probes, three voted protection channels, trip relay and fuel shut-off valves, with six numbered check points A B C D PROTECTION A B C IN TEST TEST SPEED CONTROL 2oo3 TRIP FUEL IN TO ENGINE SHUT-OFF METERING LEVEL RATE SPEED / TIME 01SEPARATE PATHown probes, logic, trip path 022-OUT-OF-3 VOTINGone channel down, alarm only 03RATE AND LEVELrate trip before level 04SIMULATED SPEEDone channel at a time 05DE-ENERGISE TO TRIPfuel shut-off valves close 06LATCHED, RECORDEDreset when the cause is clear

Overspeed protection is the one turbine function that has to work the first time it is needed.

How I approach an overspeed protection check:

  1. 1.Separate from the speed control. Own probes, own logic, own trip path.
  2. 2.Three channels, voted two out of three. One failed channel gives an alarm, two agree and it trips.
  3. 3.Overspeed and over-acceleration. The rate trip acts before the level is reached.
  4. 4.Simulated speed test, one channel at a time. The other two keep protecting the unit.
  5. 5.De-energise to trip. Remove the power and the fuel shut-off valves close.
  6. 6.Latched and recorded. No reset until the cause is clear.

What's on your list? Do you prove the full trip path to the valves, or stop at the relay?

· Week 48

Safety rules

No permit, no work.
No permit, no work. Cutaway of a gas turbine package with every energy source isolated and locked by the site under the client permit: permit on a clipboard, electrical breaker locked in the MCC, fuel gas block valves locked, the site lock box, a laptop with control logic next to a signed change approval, the enclosure door with the fire suppression cylinders inhibited, and a stop sign. Six numbered points. STARTER TURBINE ENCLOSURE FUEL GAS OFF MCC PERMIT SITE LOCK BOX INH FIRE SUPPRESSION CHANGE STOP 01PERMIT FIRSTrisk assessment, toolbox talk 02EVERY SOURCE ISOLATEDfuel, power, oil, air, rotation 03SITE ISOLATIONSchecked before I sign on 04LOGIC CHANGESclient approval, on record 05ENCLOSURE ENTRYper site inhibit procedure 06STOP THE JOBanyone, any time, no blame

No permit, no work. That is where safety on a turbine job starts.

How I work on every Telic assignment:

  1. 1.Permit first. No work starts without the site permit, risk assessment and toolbox talk.
  2. 2.Every source isolated as the job requires. Electrical, fuel gas, liquid fuel, hydraulic, lube oil, air, rotation, heat and fire suppression.
  3. 3.Isolations by the site. The site's isolation authority isolates and locks. I go through the isolation list before I sign on.
  4. 4.No change to logic or settings without the client's written approval and a record.
  5. 5.Enclosure entry only with the site's fire suppression and gas detection inhibit procedure.
  6. 6.Stop the job. Anyone on site can, any time, no blame.

Where client and Telic rules differ, the strictest applies.

Which part of the permit do you always check twice?

· Week 47

DLE mapping explained

A DLE engine runs in a narrow window.
A narrow window. Mapping finds it. Cross-section of a triple annular lean premix DLE combustor: premixer module through the casing with three cups A, B and C feeding three flame zones between the inner and outer liner, HPT nozzle at the exit. Next to it the flame temperature windows of the five LM6000 burner modes B, BC/2, BC, AB and ABC, each with a hot edge and a lean edge, and the schedule running through them: bleed closes across each window, at the hot zero-bleed corner the control stages up and flame temperature drops into the next mode. Six numbered points. FROM COMPRESSOR A B C A B C DOME HPT PREMIXER MODULE POWER FLAME TEMPERATURE LM6000 BURNER MODES · SHAPE ONLY EACH WINDOW: MAX BLEED LEFT, ZERO BLEED RIGHT B BC/2 BC AB ABC HOT EDGE · NOx / DYNAMICS LEAN EDGE · CO / UHC STAGE UP MAX BLEED ZERO BLEED 01THREE FLAME RINGSA outer, B pilot, C inner 02BURNER MODESB always lit, A and C staged in 03LEAN EDGECO and UHC, then blowout 04HOT EDGENOx or dynamics, first one wins 05WINDOW PER MODEeach mode has its own 06THE SCHEDULEbleed holds it, stage up at the corner

A DLE engine runs in a narrow window. Mapping is how you find it. And there is one per burner mode.

  1. 1.Three flame rings. Outer A, pilot B, inner C. Only the pilot ring is always fuelled.
  2. 2.Burner modes. Rings are staged in as power goes up. On an LM6000: B, BC/2, BC, AB, ABC.
  3. 3.Lean limit. Too cold: CO and unburnt hydrocarbons climb, then flame-out.
  4. 4.Hot limit. Too hot: NOx climbs and combustion dynamics rise. Whichever comes first sets the edge.
  5. 5.A window per mode. Each mode has its own window, and it moves with power.
  6. 6.The schedule. Set inside every window with margin. Bleed walks the engine across it, and at the corner of the window the control stages up.

How do you prepare a unit for mapping? What do you check first?

· Week 46

Anti-surge control

Anti-surge control, in plain words.
Keeping the compressor out of surge. Three-quarter view of an aeroderivative gas turbine driving a centrifugal compressor with impeller cutaway, its suction and discharge lines and the recycle loop through cooler and anti-surge valve with the gas flow shown, plus a compressor map, six numbered points GAS TURBINE COMPRESSOR FT PT TT PT TT ASC SUCTION DISCHARGE RECYCLE COOLER FLOW HEAD (PRESSURE RISE) SURGE OP SPEED 01SURGE LINEflow too low, flow reverses 02CONTROL LINEmargin to the surge line 03OPERATING POINTflow, pressure, temperature 04RECYCLE VALVEdischarge back to suction 05START AND STOPopen on start and trip 06SURGE DETECTEDvalve holds until reset

Anti-surge control, in plain words.

A centrifugal compressor needs a minimum flow. Below it the flow breaks down and reverses. That is surge.

How the control keeps it away:

  1. 1.Surge line. The left edge of the compressor map. Past it, the machine is unstable.
  2. 2.Control line. A margin to the right of the surge line. The controller acts here.
  3. 3.Operating point. Calculated live from suction flow, pressure, temperature and head.
  4. 4.Recycle valve. Opens at the control line and sends discharge gas back to suction, normally via a cooler.
  5. 5.Start and stop. Open on start, ramps closed once online, fully open on a stop or trip.
  6. 6.Surge detected. The valve holds a minimum position until the operator resets it.

What do you check first when you commission anti-surge? Valve stroke time, transmitter ranges, or the map?

· Week 45

VSV schedule explained

An LM2500 compressor is built for full speed.
What the VSV schedule really does. Three-quarter front view of an LM2500 high pressure compressor with a cutaway of the variable stator vanes, actuator, VG pump and VSV schedule, six numbered points GEARBOX CONTROL VSV SCHEDULE OPEN CLOSED NGG CORRECTED FOR T2 → TOO OPEN STALL TOO CLOSED HIGH NGG 01CORRECTED SPEEDNGG corrected for T2 02VSV STAGESseven rows, move as one 03SCHEDULEclosed low, open at power 04VG PUMP + SERVOon the transfer gearbox 05TWO ACTUATORSone each side of the casing 06LVDT FEEDBACKdemand vs position

An LM2500 compressor is built for full speed. The variable stator vanes make it work at every other speed.

  1. 1.Input: gas generator speed (NGG), corrected for inlet temperature (T2). Output: VSV position.
  2. 2.Of 16 stages, seven rows are variable: the inlet guide vane row plus stages 1 to 6. LM2500+: stage 0 added, 17 stages, eight rows.
  3. 3.Closed at low corrected speed, opening as speed rises. Off schedule, too open: front stages stall. Too closed: NGG runs high for the power, towards overspeed.
  4. 4.The gearbox-driven VG pump feeds the actuators through a servo valve.
  5. 5.Each row's vanes are connected by linkages to an actuation ring. One hydraulic actuator per side moves all rings, via a master lever (LM2500) or torque shaft (LM2500+).
  6. 6.Position feedback (LVDTs on the LM2500+) is checked against demand.

How do you explain the VSVs to new operators?

· Week 44

Loop checks LM

A loop check is not done when the HMI shows a number.
Loop checks start at the sensor. Signal loops from sensors on an aeroderivative gas turbine package through the junction box and control cabinet to the HMI, with six numbered loop check points PACKAGE CONTROL ROOM GAS GENERATOR PT LUBE OIL JB HMI 01AT THE SENSORnot at the terminal 02TAG, RANGE, UNITSsame at card and HMI 03THERMOCOUPLEStype K all the way 04RTD WIRING3 or 4 wire right through 05SPEED, VIBRATIONsignal in at the pickup 06ALARM AND TRIPcheck the action

A loop check is not done when the HMI shows a number.

How I approach loop checks on an LM package:

  1. 1.Start at the sensor, not the terminal. Inject at the field end, so junction box, marshalling and I/O are proven too.
  2. 2.Tag, range and units the same on the card, in the application and on the HMI.
  3. 3.Thermocouples: right extension cable and connectors all the way (type K on the LM2500), polarity checked.
  4. 4.RTD wiring: 3 or 4 wire right through, so lead resistance is compensated.
  5. 5.Speed and vibration: signal in at the pickup end, conditioner matched to the sensor.
  6. 6.Alarm and trip: drive every signal through both. Check the action, not only the reading.

What do you check first in a loop check? And what would you add?

· Week 43

Load sharing segments

A Woodward easYgen / LS-6 power management system looks complex on the single line.
Load sharing, one segment at a time. Single line diagram of a generator power management system with genset controls, breaker controls, a load share bus and two busbar segments, with six numbered callouts LOAD SHARE BUS SEGMENT 1 SEGMENT 2 TIE LS-6 MAINS LS-6 G AVR GOV easYgen G AVR GOV easYgen G AVR GOV easYgen G AVR GOV easYgen 01EASYGENone per set, own breaker 02LS-6tie, coupler or mains breaker 03LOAD SHARE BUSCAN or Ethernet 04SEGMENTSopen tie, two busbars 05ACTIVE POWERequal % of rating 06REACTIVE POWERthrough the voltage regulator

A Woodward easYgen / LS-6 power management system looks complex on the single line. The logic is simple.

How I explain it:

  1. 1.Each generator has its own easYgen. It synchronises and closes its own breaker.
  2. 2.Every other breaker that must synchronise (tie, bus coupler, mains) gets its own LS-6. It measures both sides and closes in sync or onto a dead bus.
  3. 3.All units talk on one load share bus, CAN or Ethernet.
  4. 4.Open tie breakers split the busbar into segments. Sets only share load with sets on the same segment.
  5. 5.kW is shared as an equal percentage of rating, not equal kW. A smaller set carries less.
  6. 6.kvar is shared the same way, through the voltage regulator.

How do you test the segment logic at commissioning? Breaker by breaker on the live bus, or simulated first?

· Week 42

Commissioning handover dossier

A start-up is not finished when the unit runs.
A start-up ends at the handover. Open turbine control cabinet with laptop, transmitter and calibrator, trip pushbutton station, trend display and punch list, with six numbered handover items 01AS-LEFT SOFTWAREbacked up, version labelled 02LOOP CHECK SHEETSsigned per tag 03CALIBRATIONtransmitters and valves 04TRIP TEST RECORDSevery one witnessed 05BASELINE DATALOGnormal start, loaded run 06PUNCH LISTowner and date per item

A start-up is not finished when the unit runs. It is finished when the operator can run it without me.

What I leave behind at commissioning handover:

  1. 1.As-left software, backed up, version and date labelled
  2. 2.Loop check sheets, signed per tag
  3. 3.Calibration records for transmitters and valves
  4. 4.Trip test records, every one witnessed
  5. 5.Baseline datalog of a normal start and a loaded run
  6. 6.Punch list with owner and date per item, nothing open by word of mouth

And one walk-through at the control cabinet and field instrumentation with the people who stay on site.

What do you want on your desk at handover? What would you add, or ask for first?

Archive

Older notes

  1. · Week 41 Redundant controls health Redundancy hides failures.
  2. · Week 40 GG exchange checks After a gas generator exchange the engine is new.

My current job, 4k inspections offshore UK, is wrapping up, so I have room for the next one. Overspeed protection to prove before a start-up? Send me a message, happy to support.

Send the start date, estimated duration, scope, systems on site and location. You get availability and an estimate the same working day.

Request availability

Question from purchasing or compliance? Company details, insurance, HSE and quality policies and procedures are on the Working with Telic page.

Remco Petersen
Telic Engineering B.V.
Markenplein 24, 1011 MV Amsterdam
The Netherlands
remco.petersen@telic-engineering.nl
+31 6 51345316
Telic Engineering on LinkedIn
Remco Petersen on LinkedIn