Commissioning handover dossier

Week 42Remco Petersen

Sheet 42

Field note, first posted on LinkedIn.

A start-up ends at the handover. Open turbine control cabinet with laptop, transmitter and calibrator, trip pushbutton station, trend display and punch list, with six numbered handover items 01AS-LEFT SOFTWAREbacked up, version labelled 02LOOP CHECK SHEETSsigned per tag 03CALIBRATIONtransmitters and valves 04TRIP TEST RECORDSevery one witnessed 05BASELINE DATALOGnormal start, loaded run 06PUNCH LISTowner and date per item

A start-up is not finished when the unit runs. It is finished when the operator can run it without me.

What I leave behind at commissioning handover:

  1. 1.As-left software, backed up, version and date labelled
  2. 2.Loop check sheets, signed per tag
  3. 3.Calibration records for transmitters and valves
  4. 4.Trip test records, every one witnessed
  5. 5.Baseline datalog of a normal start and a loaded run
  6. 6.Punch list with owner and date per item, nothing open by word of mouth

And one walk-through at the control cabinet and field instrumentation with the people who stay on site.

What do you want on your desk at handover? What would you add, or ask for first?

Start-up or engine exchange coming up and you need a controls engineer who closes it out properly? Send me a message, happy to support.

Send the start date, estimated duration, scope, systems on site and location. You get availability and an estimate the same working day.

Request availability

Question from purchasing or compliance? Company details, insurance, HSE and quality policies and procedures are on the Working with Telic page.

Remco Petersen
Telic Engineering B.V.
Markenplein 24, 1011 MV Amsterdam
The Netherlands
remco.petersen@telic-engineering.nl
+31 6 51345316
Telic Engineering on LinkedIn
Remco Petersen on LinkedIn