Installation & commissioning
From setting the trailers to load tests: loop checks, functional tests, first fire, synchronising and reliability run.
Telic Engineering / Engines / TM2500
Installation, commissioning, modification and relocation of TM2500 and TM2500+ mobile units, on Woodward and GE control systems. Usually with a grid date that does not move.
The six places on a TM2500 package where most of our work happens, numbered as in the drawing at the top of the page.
By engineers who have done it before. Every job comes with a short daily report and paperwork you can use.
From setting the trailers to load tests: loop checks, functional tests, first fire, synchronising and reliability run.
Fuel forwarding, auxiliary power and plant interfaces, commissioned together with the units.
On multi-unit projects: an engineer who knows the control system inside out, next to the installation contractor.
Control and logic modifications on running fleets, such as the hot restart that avoids the four-hour lockout.
A unit moved to a new site: reconnect, re-check, recommission.
Staying on through the first weeks of running, until the operating crew is confident with the units.
What we have actually worked on. If your TM2500 package is not on it, ask.
Taken from our track record, newest first. No client or site names here; ask and we tell you, under NDA if needed.
| Period | Work | Equipment | Systems | Location |
|---|---|---|---|---|
| Jan–Apr 2020 | Commissioning | 5× gas turbines | TM2500, RX3i | Ghana |
| May–Jul 2017 | Commissioning | 4× gas turbines | TM2500, MicroNet | Argentina |
| Oct–Dec 2016 | Commissioning | 2× gas turbines | TM2500, MicroNet | Saudi Arabia |
| May–Jul 2016 | Modification | 2× gas turbines | TM2500, MicroNet | Saudi Arabia |
| Jul 2015–Mar 2016 | Commissioning, balance of plant | 5× gas turbines | TM2500, MicroNet | Saudi Arabia |
| May–Jun 2015 | Commissioning, control TA | 12× gas turbines | LM6000, TM2500, MicroNet | Egypt |
| Jun–Jul 2014 | Commissioning | 3× gas turbines | TM2500, MicroNet | Algeria |
| May–Sep 2013 | Installation and commissioning | 12× gas turbines | TM2500, MicroNet | Algeria |
| Apr–Nov 2012 | Installation and commissioning | Gas turbines | TM2500, MicroNet | Algeria |
Both. Much of our TM2500 work is for OEMs, packagers and service providers, as their field engineer. We also work directly for operators and owners. Where an OEM service contract is in place, we work alongside the OEM team, not around it.
Both. We are experts on Woodward and GE control systems: Woodward MicroNet, GE Mark VI and Mark VIe, and GE PAC RX3i.
Yes. For multi-unit projects we add contractors from our own network, under our agreement, our insurance and our reporting, with one contact for you.
Send the start date, location and scope and you get availability and an estimate the same working day. Offshore certificates (OPITO BOSIET/FOET, MIST, offshore medical) are kept current, so paperwork is not what holds you up.
Yes. For campaigns or several units at once we add contractors from our own network, under our agreement, our insurance and our reporting. How resource supply works.
Send the start date, estimated duration, scope, systems on site and location. You get availability and an estimate the same working day.